Enabling and adoptable infrastructure works to support future residential and commercial development.

Key Features

  • Earthworks and formation preparation.
  • S38 carriageway and footway construction.
  • Demolition and licensed asbestos removal.
  • New culvert and mammal tunnels over watercourse.
  • Live tie‑in to adjacent spine road.

 

Challenges

  • Deep excavations and proximity to a live watercourse.
  • Ecological constraints, including mammal movements and tree protection.
  • Unmarked asbestos buildings discovered during devegetation.
  • Interfaces with an adjacent active development.

Delivery Approach

Early pre‑construction planning aligned long‑lead materials and specialist subcontract packages with the construction sequence.

Weekly coordination with the client team maintained progress and effectively managed third‑party interfaces.

GPS machine control and CBR testing supported accurate delivery, while safe systems of work and environmental controls ensured compliance throughout the scheme.

 

Outcome

  • S38 spine road completed to GCC specification and approved immediately.
  • Project delivered within budget and ahead of programme.
  • Successful management of deep drainage, asbestos removal and third‑party interfaces.